Silvertip Crude Oil Pipeline
This article is part of the Global Fossil Infrastructure Tracker, a project of Global Energy Monitor and the Center for Media and Democracy. |
Sub-articles: |
Silvertip Crude Oil Pipeline is an oil pipeline in the United States.[1]
Contents
Location
The pipeline runs from the Elk Basin, Wyoming, to Billings, Montana, crossing under the Yellowstone River.
Project Details
- Operator: ExxonMobil[1]
- Current capacity: 40,000 barrels per day
- Proposed capacity:
- Length: 69 miles (111 kilometers)
- Status: Operating
- Start Year:
Background
The Silvertip Pipeline is a 12-inch pipeline approximately 69 miles in length that runs from the Elk Basin, Wyoming, to Billings, Montana. Receipt points include Cenex Front Range Pipeline, Glacier Crude Oil Pipeline, Marathon Pipeline, and the Express Oil Pipeline System at Edgar Station, Montana. Deliveries are to Cenex at Laurel in Montana, and ExxonMobil Billings Refinery in Montana.[1]
Spills
In 2011, over 1,500 barrels of oil leaked from the pipeline during a flood.[1] After the spill, Exxon admitted the Silver Tip pipeline was also used to move oil sands crude to Billings, since the placement of a new tank farm in 2006.[2]
Articles and resources
References
- ↑ 1.0 1.1 1.2 1.3 Silvertip Crude Oil Pipeline, A Barrel Full, accessed September 2017
- ↑ Anthony Swift, "Tar sands implicated in Yellowstone River pipeline spill," NRDC, July 15, 2011