South Tunisia Gas Project pipeline is a natural gas pipeline, currently under construction, running from Nawara gas field to Gabès, Tunisia.

Location

The pipeline runs from Nawara gas field, Tataouine governorate, to Gabès, Gabès governorate, Tunisia.

Loading map...

Project Details

  • Operator: Entreprise Tunisienne d'Activités Pétrolières (ETAP) (50%) and OMV Tunisia (50%)
  • Parent Company: Government of Tunisia and OMV
  • Proposed capacity: 3.65 billion cubic meters per year
  • Length: 370 kilometers
  • Status: Construction
  • Start Year: 2019

Background

The South Tunisia Development Project (or Nawara Development Project) is aimed at developing the Nawara gas field in southern Tunisia. Part of the project is the construction of a 24-inch, 370-kilometer gas pipeline from the Nawara field to the port city of Gabès.[1][2][3]

Construction on the pipeline began in 2015.[4] In October 2018 the Tunisian Minister of Energy stated that the project would become operational in June 2019.[5]

Articles and resources

References

  1. Nawara Development Project, Wikipedia, accessed July 2018.
  2. South Tunisian Gas Project (STGP) / Nawara Project, Hydrocarbons Technology, accessed July 2018.
  3. Executive Summary of the Environmental and Social Impact Statement, South Tunisian Gas Pipeline - Nawara, African Development Bank, April 2014.
  4. Nawara pipeline construction project in Tunisia on track, Construction Review, 19 Apr. 2016.
  5. Nawara field in Tataouine, operational in June 2019, almasdar.tn, Oct. 23, 2018

Related SourceWatch articles

External resources

External articles